Implementation project of the non-executed secondary sewage lines for Contract (14M-1) for Al Wahah neighborhoods (1, 2, 3) in Jeddah.

About Project

Construction of the sewerage network in Alwaha district in Jeddah - Contract No.14 m-1 , scope of work include installation GRB pipelines with diameters of 300 mm, 400 mm and 500 mm, with a total length of 7100 meters for the gravity network works. This includes the construction of GRB manholes totaling 166 manholes, covering excavation, backfilling, and asphalt works within the scope of the project contract according to the specifications of the National Water Company.

Client

National Water Company.

Project Value

SAR 22,713,483

Start and End date

From 22 Nov 2024 to 22 Nov 2026