Transition Line To Feed Water To Projects of The Diriyah Gate Development Authority

About Project

Construction of transmission pipe line 1200 mm with total length 23 km to feed water to projects of the Diriyah gate development authority, scope of work include execution micro tunneling works under main road on Riyadh with total length 1400 m , execution of concrete valve chamber for butterfly valves , air valves, washout air valves ,flow meter and flow control valve with Scada system for all valves with connection to existing Scada system at TGNW tank location and asphalt works on main roads.

Client

National Water Company.

Project Value

SAR 122,372,880.00

Start and End date

From 12 July 2022 To 12 July 2024

Project Photos

Work with us

We help you achieve your goals and bring your ideas to life. We are a dedicated team of professionals who are committed to providing the best solutions for our clients. Let us collaborate and create something amazing together.